Chlorinated solvent remediation Veenendaal Holland

28 Km of PE tubing was required to connect nearly 600 airsparge filters on a 0,7 million Euro remediation in Veenendaal, Holland. The system, pilot-tested, designed and instrumented by Geo & Hydro met all the time and end concentration criteria, which were agreed with site owner and state authority before the project commenced.