PB2
Chlorinated solvent remediation Veenendaal Holland
28 Km of PE tubing was required to connect nearly 600 airsparge filters on a 0,7
million Euro remediation in Veenendaal, Holland.
The system, pilot-tested, designed and instrumented by Geo & Hydro met all the
time and end concentration criteria, which were agreed with site owner and state
authority before the project commenced.